What does “all exterior doors” include on a commercial painting quote?

Count faces, frame openings, overhead doors and bollards separately. This sample scope gives the owner and bidder the same list to walk.

Blue roll-up storage doors in a white masonry wall, with a scissor lift parked in the aisle
Blue roll-up doors and separate white surrounds. Count the moving doors and their surrounds on different lines.

Count openings first, then write down what the crew is asked to coat at each one. A pair of entrance doors can mean two exposed door faces and one shared frame. An overhead loading door has a very different shape and working window. The bollards alongside it are another item altogether. Counting them all as doors makes a bid difficult to check.

Work through one loading area

Suppose a service elevation has two single personnel doors, one double-leaf entrance, one roll-up door and four bollards. For the personnel and entrance doors together, a sample quote line could read “four outward-facing door faces across three openings, plus the exposed exterior face of three frame assemblies.” That wording gives the owner something to verify on site.

Now add a separate line for “one roll-up door, exterior face, Bay 2.” State whether the visible side surrounds or head are included. List the four bollards on their own line. If only two bollards have worn through the existing finish, photograph those two and ask the estimator to identify any different preparation in the quote. These quantities describe an illustrative loading area.

Name the parts that change how work gets done

Agree whether edges, interior faces and hardware are included, protected or left alone. A door that must stay closed to secure a storage room raises a different question from one where the manager can arrange a closure. Write down who will open or secure each area and what access the painter can assume. Have the site operator identify equipment and parts that must remain untouched.

The self-storage project photos make the distinction between the blue roll-up doors, their surrounds and the white walls easy to see. A photo taken straight down the row also helps spot openings that differ from the rest. Put those exceptions on separate lines before multiplying a typical bay.

Check the count from the other end

Give the marked-up list to somebody who did not do the first count. Ask them to find each location and tell you what will change colour. If they cannot identify which face or opening a line describes, the crew will have the same problem. Bring the corrected list to the commercial site walkthrough and use it again at handback.

Your project checklist